技术标的编写应该注意哪些细节处理?

网址:http://www.biaoshufang.com 时间:2020-04-20

1、检查工程概略描绘的精确与否。

1. Check the accuracy of the general description of the works.
2、计划开竣工日期应符合投标文件中工期安排与规则,分项工程的阶段工期、节点工期满意投标文件规则。工期提早要合理,要有相应办法,不能提早的决不提早,如铺架工程工期。
2. The planned commencement and completion date shall conform to the schedule and rules in the bidding document, and the stage schedule and node schedule of the subdivisional works shall be satisfied with the bidding document rules. The construction period shall be reasonable in advance, and corresponding measures shall be taken. If it cannot be done in advance, it shall never be done in advance, such as the construction period of the erecting works.
3、工期的文字叙说、施工顺序安排与“形象进展图”、“横道图”、“网络图”应共同,特别是铺架工程工期要针对具体情况细心安排,以免造成与实际情况不符的现象。
3. The text narration and construction sequence arrangement of the construction period shall be in common with the "image progress chart", "bar chart" and "network chart", especially the construction period of the erecting works shall be carefully arranged according to the specific situation, so as not to cause the phenomenon inconsistent with the actual situation.
4、整体部署:施工部队及首要负责人与资审计划要共同,文字叙说与“平面图”、“安排机构框图”、“人员简历”及拟人职务等符合。
4. Overall deployment: the construction force and the chief person in charge shall work together with the qualification review plan, and the narrative shall be in line with the "plan", "organization chart", "personnel resume" and personified post.
5、施工计划与施工办法、工艺一定要匹配。
5. The construction plan must match with the construction method and process.
6、施工计划与投标文件要求、投标书有关许诺共同。资料供应与甲方要求共同:共同代储代运、甲方供应或投标采购。暂时通讯计划按投标文件要求办理。(有要求架空线的,不能按无线报价)。施工部队数量应按照投标文件规则装备。
6. The construction plan is in common with the requirements of the bidding document and the promises related to the bidding document. Data supply and Party A's requirements are the same: joint storage and transportation, Party A's supply or bidding procurement. The temporary communication plan shall be handled according to the requirements of the bidding document. (if overhead line is required, it cannot be quoted by wireless). The number of construction units shall be equipped in accordance with the bidding document rules.
7、工程进展计划:总工期、要害工程工期应满意投标文件要求。
7. Project progress plan: the total construction period and critical project construction period shall meet the requirements of the bidding document.
8、特别工程项目是否有特别安排:在冬季施工的项目办法要得当,影响质量的必须罢工,胀大土雨季要考虑罢工,跨过季节性河流的桥涵基础雨季前要完结,工序、工期安排要合理。
8. Whether there is special arrangement for special engineering projects: if the project method of construction in winter is proper, strikes must be taken for those affecting the quality, strikes shall be considered for swelling soil in rainy season, bridges and culverts crossing seasonal rivers shall be completed before rainy season, and the process and construction period shall be arranged reasonably.
9、留意:“网络图”工序安排是否合理,要害线路是否正确。
9. Note: whether the process arrangement of "network diagram" is reasonable and whether the critical line is correct.
10、检查“网络图”如需中断时,是否正确表示,各项目完毕是否归到相应方位,虚作业是否合理。
10. Check whether the "network diagram" is correctly represented when it needs to be interrupted, whether the completion of each project is in the corresponding position, and whether the virtual operation is reasonable.
专业标书制作公司
11、“形象进展图”、“横道图”、“网络图“中工程项目是否齐全:路基、桥涵、轨道或路面、房屋、给排水及站场设备、大临等。
11. Whether the projects in the "image progress chart", "bar chart" and "network chart" are complete: subgrade, bridge and culvert, track or pavement, housing, water supply and drainage, station and yard equipment, Dalin, etc.
12、“平面图”是否按投标文件安置了部队驻地、施工场所及大临设备等方位,驻地、施工场所及大临工程占地数量及工程数量是否与文字叙说相符。
12. Whether the "plan" has arranged the location of the army station, construction site and large temporary equipment according to the bidding document, and whether the land occupation and project quantity of the station, construction site and large temporary project are consistent with the words.
13、劳动力、资料计划及机械设备、检测实验仪器表是否齐全。
13. Whether the labor force, data plan, mechanical equipment and test instrument list are complete.
14、劳动力、资料是否按照投标要求编制了年、季、月计划。
14. Whether the annual, quarterly and monthly plans for labor force and data are prepared in accordance with the bidding requirements.
15、劳动力装备与劳动力曲线是否符合,总工天数量与预算表中总工天数量差异要合理。
15. Whether the labor force equipment and labor force curve are consistent, and the difference between the total number of working days and the total number of working days in the budget table should be reasonable.
16、标书中的施工计划、施工办法描绘是否符合规划文件及标书要求,采用的数据是否与规划共同。
16. Whether the construction plan and construction method described in the bidding document meet the requirements of planning documents and bidding documents, and whether the data used are common with the planning.
17、施工办法和工艺的描绘是否符合现行规划规范和现行规划标准。
17. Whether the description of construction method and process conforms to the current planning specifications and standards.
18、是否有防汛办法(假如需求),办法是否有力、具体、可行。
18. Whether there are flood control methods (if required), and whether the methods are powerful, specific and feasible.
19、是否有治安、消防办法及农忙季节劳动力调节办法。
19. Whether there are public security, fire control methods and labor adjustment methods in busy farming season.
20、首要工程资料数量与预算表工料机统计表数量是否符合共同。
20. Whether the quantity of primary engineering data is consistent with the quantity of statistical table of labor, materials and machines in the budget table.
21、机械设备、检测实验仪器表中设备品种、型号与施工办法、工艺描绘是否共同,数量是否满意工程施行需求。
21. Whether the type, model, construction method and process description of the equipment in the list of mechanical equipment and testing instruments are common, and whether the quantity is satisfied with the project implementation requirements.
22、施工办法、工艺的文字描绘及框图与施工计划是否共同,与要点工程施工安排安排的工艺描绘是否共同;总进展图与要点工程进展图是否共同。
22. Whether the construction method, process description, block diagram and construction plan are the same, whether they are the same with the process description of key project construction arrangement; whether the general progress chart and key project progress chart are the same.
23、施工安排及施工进展安排的叙说与质量确保办法、安全确保办法、工期确保办法叙说是否共同。
23. Whether the narration of construction arrangement and construction progress arrangement is common with the narration of quality assurance method, safety assurance method and construction period assurance method.
24、投标文件的首要工程项目工艺框图是否齐全。
24. Whether the process block diagram of the main project in the bidding document is complete.
25、首要工程项目的施工办法与规划单位的主张计划是否共同,理由是否合理、充沛。
25. Whether the construction method of the major project is the same as the plan advocated by the planning unit, and whether the reasons are reasonable and abundant.
26、施工计划、办法是否考虑与相邻标段、前后工序的配合与衔接。
26. Whether the construction plan and method consider the cooperation and connection with the adjacent bid section and the previous and subsequent processes.
27、暂时工程安置是否合理,数量是否满意施工需求及投标文件要求。暂时占地方位及数量是否符合投标文件的规则。
27. Whether the temporary project arrangement is reasonable, whether the quantity is satisfied with the construction demand and the requirements of the bidding document. Whether the location and quantity of temporary land occupation conform to the rules of bidding documents.
28、过渡计划是否合理、可行,与投标文件及规划目的是否相符。
28. Whether the transition plan is reasonable and feasible, and whether it is consistent with the bidding documents and planning purposes.